Site Preparation Summary

2016-2018 Site Preparation Overview

NGA Site Image_0012

Summary of Milestones

January 9, 2018: SLDC's Minority Business Department, in conjunction with MOKAN and Next NGA West - St. Louis hosted a Construction Town Hall Meeting with at the William J. Harrison Education Center. View the presenter's presentations.

October 20, 2017: Final demolition bid in process. Contract to be awarded early November. Last Remaining utility work is near completion.

October 11, 2017: To date, over 8,100 truckloads have removed more than 190,000 tons of soil material offsite.

October 6, 2017: Initial excavation and sampling activities for 8 of 27 City Blocks is complete.